AIP is working across Ireland to develop wind farms, generate clean renewable energy and provide long-term additional incomes for farm families
What makes up a wind farm?
A wind farm has a number of important parts, all of which are needed to make the project work. They include:
What are the steps in developing a wind farm?
A wind farm usually takes a number of years to develop from when the optimum site is first identified, through to when the wind farm begins operating. These are the main steps in the process:
1. Site identification
Site identification is the process we go through to find optimum sites for wind farms. Many different factors go into deciding which sites can potentially make a good wind farm site. Wind farms need a lot of land, and the land that is most suitable has to be far enough away from houses, roads, archaeological sites and nature protection areas. The optimum sites must also be close enough to a part of the national electricity grid that has the capacity to take the electricity that the wind farm generates.
2. Land agreements
Land agreements are the option and lease contracts we enter into with landowners who want to partner with AIP to make their land available for a wind farm. After we explain how and why we have identified their lands as having potential, we spend time getting to know the owners of the land and their neighbours and give everyone a chance to ask whatever questions they might have. AIP encourage every landowner to seek independent legal advice and make a contribution towards the cost of this.
3. Environmental surveys
Environmental surveys take place over a two-year period, before submitting a planning permission application. Bird surveys are usually the first to start, usually in March or October, which become key milestones for progressing a project. Other ecological, archaeological, hydrological, noise and other surveys take place later along with other types of assessments required to prepare an environmental report that is submitted along with the planning application. Typically, the surveys inform the locations of the turbines and it is not possible to understand where and how many turbines are planned until the surveys are completed.
4. Community consultation
Community consultation is a very important stage as it allows us share with the local community, details of where the proposed project will be located and what it might consist of. We try to engage with the local community at the earliest opportunity, but only when we know a sufficient amount ourselves about the proposed project to make that engagement and consultation meaningful and worthwhile.
5. Planning
Planning is the process where we submit a formal planning permission application for the proposed wind farm. It gives every member of the public an opportunity to formally comment on the project before the local Planning Authority or An Bord Pleanála finally make a decision on whether the project should proceed or not.
6. Grid connection
A grid connection is vital to export electricity from a wind farm to the national grid, and an application to connect to the grid and eventually export electricity can only be applied for after planning permission has been granted. Grid connections will be allocated at regular intervals over the coming years, and once our application is successful, AIP would have the right to “plug in” our project to the national grid and begin to export power.
7. Community gain
Community gain is the way the benefits of the project get divided amongst near neighbours and the local community and usually starts before construction starts, and continues throughout the life of the wind farm. AIP is committed to tailoring its community gain schemes to each individual community and recognises that no two communities are the same. We believe the best community gain schemes are those that the local community themselves help design and we try to involve the community in this through the pre-construction stages of every project.
8. Construction
Construction usually takes about 12 months after a route to market for the electricity has been secured. With our construction and development partners, it is AIP policy to use as much local labour, machinery and local contractors in the construction of its projects, whenever possible. Although all wind turbines are imported into Ireland, most of the construction is now carried out by Irish workers and many Irish firms have come to specialise in wind farm construction.
9. Operation
A wind farm comes into operations when it has been built and fully commissioned and is exporting clean, green electricity to the national grid. Wind farms are now being designed to last for 25-30 years with advances in technology and engineering.